Category Archives: Engineering

Nevada Copper Pumpkin Hollow Project hosted a Public Presentation on July 22

Pumpkin Hollow Project staff met with the local community on July 22, 2015 at 6 PM in the Pioneer Crossing Convention Center for an update on the progress of the Project and revised feasibility study.  Tim Dyhr, Vice President of Environment & External Relations gave a PowerPoint presentation full of updates and information on the Pumpkin Hollow Project with a Q&A session to an audience of over one hundred (100) people.  Seven (7) station tables were set up with Nevada Copper managers and staff to answer questions regarding; Mining, Engineering & Construction, Procurement, Safety, Environment, Processing and Geology.

Key accomplishments to date include:

  • Completed production headframe and hoist
  • Completed 24-foot diameter production-sized shaft to 1900 feet below ground
  • Developed 500+ feet of underground drift on the 1900 haulage level
  • Commenced underground drilling from two stations on the 1900 level
  • Installed electrical substation, ventilation fans, dewatering pumps and other underground infrastructure in the 1900 level
  • Resumed surface drilling in the two open pit zones of the project
  • Completed the “Integrated Feasibility Study” for open pit and underground mining operations with a single 70,000 ton per day processing facility (concentrator) which included;
  • Added drill results from drilling not included in the previous feasibility studies
  • Added improvements to construction, mining and processing

Tim Dyhr pointed out the tasks and steps the Pumpkin Hollow Project must first complete before production can begin:

  • Finalize the land conveyance and state permitting
  • Secure financing for the project
  • Complete the main production shaft to 2,160 feet below the surface
  • Sink a second ventilation and emergency egress shaft
  • Develop the underground mine access drifts
  • Construct processing facilities
  • Construct water, power and road access, as well as shops and offices
  • Recruit and train a workforce for mining and milling operations
  • Obtain and assemble mine shovels, excavators and haul trucks and other equipment for mining
  • Initiate underground and open pit mining

A Safety Award “shout out” was also announced by Tim Dyhr.

Cementation, USA, Nevada Copper’s underground shaft sinking contractor, tied for first (1st) place in the Nevada Mining Association 2015 Safety Awards in the ‘Safety, Contractors’ category.   Nevada Copper, the Pumpkin Hollow Project also tied for first (1st) place in the Safety Underground Category for mine developments up to 99 employees.

http://www.nevadamining.org/safety/2015-safety-awards-release.pdf

TDyhrPres20150722

Tim Dyhr, Vice President of Environment and External Relations for Nevada Copper gives an informational updated presentation to the public.

NCU-PublicPres20150722

Greg French, Vice President Exploration and Project Development and Project Geologist, Korin Carpenter answer questions about geology and exploration at Pumpkin Hollow.

Greg French, Vice President of Exploration and Project Development and Project Geologist, Korin Carpenter answer questions about geology and exploration at Pumpkin Hollow.

The presentation also highlighted the extensive environmental studies that have been undertaken to design and operate the project in order to meet high environmental standards, as well as the environmental permitting, management and monitoring work that is ongoing to protect surface water and groundwater. Detailed reclamation plans and performance bonding (to ensure the safe and professional closure and reclamation of the mine upon completion of mining) is required before the project can be built.  These plans must be reviewed every three years by the Nevada Division of Environmental Protection.  The Yerington land conveyance, as directed by Congress, will also provide distinct opportunities to convert, rather than demolish, mine facilities such as buildings, power lines, water supply and wastewater treatment, and roads for other economic uses upon completion of mining.

MW12-WaterSample20150716rkm

Environmental Specialists Tim Leedy and Mark Hanley conduct groundwater sampling and monitoring seven days a week. Four people are presently employed at Pumpkin Hollow to manage the environmental aspects of the project including a network of 25 monitoring wells.  As the project transitions to production, additional management and monitoring will be conducted on air, water, mine rock, tailings and waste to insure that environmental resources are protected.

4-Nevada-Copper-Inc.-Pumpkin-Hollow-Project-570x257RIGHT PLACE.   RIGHT TIME.    RIGHT PEOPLE.   RIGHT WAY.

RIGHT FOR YERINGTON

 

NEVADA COPPER PUBLIC INFORMATION MEETING

JULY 22, 2015 – 6 PM – Pioneer Crossing Convention Center

 

Please join us for a public information meeting to learn about the Pumpkin Hollow Project.

On Thursday, July 9, Nevada Copper Corp. published a revised feasibility study that describes an integrated open pit and underground mine with a 70,000 ton per day process plant. Combined with the passage of the Yerington Land Conveyance by Congress in December 2014, the company sees the opportunity to develop the Integrated Project (2 mines, one mill) instead of a smaller underground mine and mill first and then a second open pit mine and mill.  The Integrated Project greatly enhances the attractiveness of and opportunity to finance the bigger project.  At the same time we have nearly completed receipt of all necessary permits to develop the integrated project.

With all of this progress, we believe it is a good time to conduct a public information meeting to let the local community know all the things we are doing and will be doing.  This includes safety, environmental and reclamation programs, management and use of groundwater and surface water, construction, mining and processing operations, and the most frequently asked questions about jobs, training and hiring.

Our goal is to ensure our mine is the safest and most productive mine with minimal impact on the environment.  We intend to convert mine facilities to other future economic uses and reclaim mine rock and tailings storage areas, and restore natural vegetation ……  A responsible approach to mining. 

Before Nevada Copper begins production and makes its first penny from copper, it needs to invest $1 billion!

We first must:

  • Complete the land conveyance and state permitting
  • Secure financing for the project
  • Complete the main production shaft to 2,160 feet below the surface
  • Sink a second ventilation-emergency egress shaft
  • Develop the underground mine access drifts (or tunnels)
  • Construct processing facilities
  • Construct water, power and road access, as well as shops and offices
  • Recruit and train a workforce for mining and milling operations
  • Obtain and assemble mine shovels, excavators and haul trucks and other equipment for mining
  • Initiate underground and open pit mining

All of Nevada will benefit from the taxes and jobs created by the Pumpkin Hollow Mine Project. Over the period of active production, the Integrated Project would create approximately 900-1,000 direct jobs. In addition, the mine will employ contractors (indirect jobs) and create other “induced” jobs such as local retail or service businesses, teachers and other public services. Total direct, indirect and induced jobs created by this project are estimated to be 3,000-3,500.

We at Nevada Copper, Pumpkin Hollow Project are committed to an on-going consultation with the Yerington community and to provide updated information on the progress of our project as it moves along.

“Right Place. Right Time. Right People. Right Way.”

 

 

NEWS RELEASES

April 23, 2015
Nevada Copper Pumpkin Hollow Project Update


April 23, 2015 – Nevada Copper Corp. (TSX: NCU) (“Nevada Copper” or the “Company”) is pleased to announce results for an initial three diamond drill holes from the current open pit drilling program and to provide a project update at the Company’s 100 percent owned Pumpkin Hollow project located near Yerington Nevada.

Highlights

  • Initial three drill holes yield strong results from new open pit drill program with particularly pleasing results from two new drill holes in the saddle zone between the North and South pits;
  • Underground drill program from 1,900 foot level to commence in May;
  • New integrated feasibility study results scheduled for release before the end of May;
  • Progress on federal land acquisition progressing according to plan with permitting progressing concurrent with land acquisition; and
  • MOU signed with large international steel company to assess opportunities to exploit Pumpkin Hollow’s significant iron ore resource.

Open Pit Drilling Results
Targeted drilling continues on the open pit deposit with the goals of testing the ultimate extent of the deposits, and identifying areas that may have economic copper mineralization but are currently categorized as waste due to lack of drill data.

The drill program which started in late February currently has three drill rigs on site. The current drill program will consist up to 74,000 feet (22,600 meters) of drilling. The first drill holes were drilled in the North Deposit to follow up open prospective areas identified in early 2013 drilling. Drill hole NC15-02 was drilled along the edge of the South deposit where mineralization was open. The table below summarizes the drilling results received for drill holes NC13-10; NC-15-01 and NC15-02. Assays for the remaining drill holes will be posted as results are received.

Greg French, Vice President of Project Development & Exploration, commented, “The current drill program is focused on the saddle zone mineralization located between the North and South pits and the open and inferred mineralized areas on the edges of the open pit deposits. The initial drill holes reported continue to expand mineralization. NC15-02 drilled along the southern portion of the South Deposit, discovered at shallow depths, a 125.5 meter zone averaging 0.42% copper. Mineralization remains open and the drill hole location in the current pit design is expected to upgrade currently classified waste material in that area.”

Drill hole NC13-10 was drilled in the Saddle Zone between the North and South open pit deposits. The mineralization correlates well with adjacent holes and bottomed in mineralization. This hole finished up a pre-collared hole from the previous 2013 drilling. The lower zone of intersected 62.4 meters (204.8 feet) true thickness averaging 0.27% copper and continues to push mineralization out and should convert mineral classification.

Drill hole NC15-01 also drilled in the Saddle Zone between the North and South deposits intersected two thick mineralized zones that correlate with adjacent holes but with slightly lower grade. The largest zone intersected 103.7 meters (340.3 feet) true thickness averaging 0.23% copper. There are also localized zones of high grade within low grade. The hole expanded mineralization within the present designed pit.

Drill hole NC15-02: South Deposit, intersected several zones of shallow mineralization along the southern edge of the deposit. The upper zones have expanded the existing mineralization. The lower zone 125.5 meters (411.7 feet @ 0.42% Cu), 88.7 meters (291feet) true thickness, is new, as several adjacent holes were only drilled as shallow pre-collars. Drill hole NC15-02 has expanded the mineralization. Follow up drilling for this expanded area and newly discovered mineralization is planned.

Hole # From
(m)
To
(m)
Length
(m)
True Length
(m)
Length
(ft)
Cu
%
Gold
(g/t)
Silver
(g/t)
Cu Equiv*
%
NC13-10 233.2 240.8 7.6 7.6 25 0.18 0.007 1.1 0.19
257.5 267.1 9.6 9.6 31.4 0.48 0.013 2.1 0.50
432.8 495.2 62.4 62.4 204.8 0.27 0.014 1.6 0.29
576.1 591.3 15.2 15.2 50 0.4 0.329 1.7 0.55
685.7 695.8 10.1 10.1 33.2 0.27 0.045 1.1 0.30
NC15-01 402.3 408.4 6.1 6.1 20 0.17 0.012 0.8 0.18
454.2 461.8 7.6 7.6 25 0.17 0.014 0.8 0.18
481.6 585.3 103.7 103.7 340.3 0.23 0.041 1.4 0.26
648.6 688.5 39.9 39.9 131 0.18 0.032 1.1 0.20
701 713.8 12.8 12.8 42 0.5 0.07 2.1 0.54
726.3 732.4 6.1 6.1 20 0.59 0.085 2.1 0.64
NC15-02 80.9 105.9 25  17.7 82.1 0.23 0.04 2.8 0.26
112.3 125 12.7 9.0 41.5 0.19 0.014 1.8 0.21
138.2 263.6 125.5  88.7 411.6 0.42 0.034 1.6 0.44
including  152.4 174.3 21.9  15.5 71.7 1.04 0.1 6.6 1.12

* Cu Equiv using Cu 3.00, Au $1200 and Ag $18; recoveries 89.3%, 67.3% and 57.3% respectively

A map showing drill holes location is shown below:


Underground Drill Program
Underground drilling of the East deposit is expected to commence in May 2015 from drill stations on the 1,900 foot level. The underground drilling program will consist of up to 26,000 feet (7,900 meters) of delineation and development drilling which will focus on further enhancing the high grade zones within the current mineral reserve, especially in areas planned for mining in the early years. This drilling program will also provide additional data for mine development designs while expanding the open mineralized areas.

Management believes that the program has the potential to improve the overall copper production grades especially in the early years while also allowing for expansion of the combined Eastern underground copper reserve boundaries that remains open in several directions.

Integrated Feasibility Study
Significant progress has been made on the Integrated Feasibility Study (“IFS”) with results targeted for release on or before May 28, 2015. The IFS envisages a single, large 70,000 tons/day concentrator with dual sources of mill feed comprising an average of 63,500 tons/day of open pit ore blended with 6,500 tons/day of high grade ore from the Eastern underground deposits. The IFS will incorporate all available current information, including approximately 32,500 feet (9,900 meters) of new drilling data from 2012 and 2013, mine plans, engineering work and updated capital and operating costs for both the open pit and underground operations associated with this development.

Federal Land Acquisition and Permits
Since passage in December of Congressional legislation that authorizes the transfer of federal lands to City and private ownership, Nevada Copper has been fully engaged with the Bureau of Land Management (“BLM”) and the City of Yerington to complete the land conveyance. The necessary agreements between the BLM and the City of Yerington are now in place to allow for the many activities to proceed toward the purchase of approximately 10,400 acres of land under the legislation. These activities include surveying, land valuation, and including compliance of the acquisition with provisions of the National Historic Preservation Act and National Environmental Policy Act. Nevada Copper and its consultants are working closely with the BLM and supplying additional resources to them as necessary to expedite the sale process.

Upon closing of the land conveyance, the City will convey 6,430 acres of private land to Nevada Copper. Adding this acreage to the 1,560 acres of private land that Nevada Copper currently controls, means that the Company will have a total of 7,990 acres (12.8 square miles) available for the large scale integrated open pit and underground mine development.

Permitting of the large open pit and underground integrated project is continuing according to plan. This permitting involves modification of our existing State air pollution control and reclamation permits to allow for the larger open pit operation and a 70,000 tons/day concentrator. Permitting is scheduled to be completed by mid-2015 concurrently with closing of the land acquisition.

Iron Concentrate Study
The Company recently executed a Memorandum of Understanding (“MOU”) with a large multi-national steel producer to assess opportunities to exploit the large Pumpkin Hollow iron resource. Measured and indicated iron mineral resources total 395 million tons grading 32.1% iron using a 20% cutoff, as disclosed in a 43-101 Technical Report filed on SEDAR in 2013. The assessments would include drill sampling, mine planning, engineering studies and metallurgical work. These studies will determine if a byproduct magnetite (iron oxide) stream from the copper tailings at a future Pumpkin Hollow concentrator would be suitable as feed for downstream iron ore processing for use in steelmaking. Other work would focus how mining plans could be modified to deliver additional magnetite in the copper concentrator feed while minimizing loss of copper. Magnetite recovery circuits are not uncommon at copper operations which contain magnetite in their mill feed. Examples are the Candelaria IOCG mine in Chile and Glencore’s Earnest Henry mine in Australia.

Along with low cost power, Pumpkin Hollow has close proximity to rail infrastructure which is important for moving the larger tonnages associated with any future iron ore production. The possibility of adding iron revenues at minimal or no cost has not been factored into any previous feasibility studies, nor in the current IFS to be released in May.

Additional Information
For further information please visit the Nevada Copper corporate website (www.nevadacopper.com) and visit our Pumpkin Hollow virtual tour.

Qualified Persons
The technical information in this release has been reviewed and approved by Gregory French, P.G., Vice-President, Exploration & Project Development, Timothy D. Arnold, P.E., Vice President Operations, and Robert McKnight, P. Eng., Executive Vice-President and CFO of Nevada Copper, all of whom are Non-independent Qualified Persons within the meaning of NI 43-101.

NEVADA COPPER CORP.

Giulio T. Bonifacio, President & CEO

Cautionary Language

This news release includes certain statements and information that may contain forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements concerning: management’s expectations of completion of the permitting and land acquisition in mid-2015, expectations as to the possible results of the Integrated Feasibility Study when completed, expectations as to any future revenues from an possible iron magnetite operation, expectations as to the results of the planned underground and surface drilling programs, as well as the Company’s plans in general at the Pumpkin Hollow Project.

Forward-looking statements or information relate to future events and future performance and include statements regarding the expectations and beliefs of management and include, but are not limited to, statements with respect to the estimation of mineral resources and reserves, the realization of mineral resources and mineral reserve estimates, the timing and amount of estimated future production, capital costs, costs of production, capital expenditures, success of mining operations, environmental risks and other mining related matters. Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information include, but are not limited to, statements or information with respect to known or unknown risks, uncertainties and other factors which may cause the actual industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.

Forward-looking statements or information are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements or information, including, without limitation, risks and uncertainties relating to: requirements for additional capital; loss of its material properties; interest rates increase; global economy; no history of production; future metals price fluctuations, speculative nature of exploration activities; periodic interruptions to exploration, development and mining activities; environmental hazards and liability; industrial accidents; failure of processing and mining equipment to perform as expected; labor disputes; supply problems; uncertainty of production and cost estimates; the interpretation of drill results and the estimation of mineral resources and reserves; changes in project parameters as plans continue to be refined; possible variations in ore reserves, grade of mineralization or recovery rates may differ from what is indicated and the difference may be material; legal and regulatory proceedings and community actions; accidents, title matters; regulatory restrictions; permitting and licensing; volatility of the market price of Common Shares; insurance; competition; hedging activities; currency fluctuations; loss of key employees; unanticipated political events in the United States, other risks of the mining industry as well as those factors discussed in the section entitled “Risk Factors” in the Company’s Annual Information Form dated March 17, 2015. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. The Company disclaims any intent or obligation to update forward-looking statements or information except as required by law, and you are referred to the full discussion of the Company’s business contained in the Company’s reports filed with the securities regulatory authorities in Canada. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that could cause results not to be as anticipated, estimated or intended. For more information on Nevada Copper and the risks and challenges of its business, investors should review Nevada Copper’s annual filings that are available at www.sedar.com.

The Company provides no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

For further information call:
Eugene Toffolo
VP, Investor Relations & Communications
Phone: 604-683-8266
Toll free: 1-877-648-8266
Email: etoffolo@nevadacopper.com
Robert McKnight, P.Eng., MBA
Executive Vice President & CFO
Phone 604-683-1309
Email: bmcknight@nevadacopper.com

 

 

Workforce Information Update 2015

articulated-dump-truck-underground-mining-19427-5567133

Nevada Copper is COMMITTED TO DEVELOPING LOCAL WORKFORCE EMPLOYMENT OPPORTUNITIES

CatHaulNevada Copper has received a number of job inquiries recently at the Pumpkin Hollow Project.  However, hiring of a construction or operations workforce is many months out, since mine financing must be secured before further construction can be undertaken.

The passage of the National Defense Authorization Act of 2014 by Congress that included Yerington Land Conveyance and the $200 million financing were exciting milestones and put us in a strong position to continue development of the project.  The Company is re-evaluating the project development strategy based on an exploration program and project studies currently underway.

The Company has constructed a 24-foot diameter, 1,900-foot deep, production-sized shaft and 600 feet of lateral development (authorization mine “tunnels”).  This work was performed by Cementation, USA, a specialized shaft-sinking contractor.  During this phase of the project, a workforce of about 30-50 people were employed.

Completion of the land conveyance in October 2015 now affords Nevada Copper an opportunity to design and develop the project in the most cost effective manner.  The project is now located entirely on private land,  is fully permitted and “shovel-ready” for development. The company continues to work on planning and engineering design.  Once the necessary financing is secured and detailed design studies have been completed, development of the project and construction could be initiated and operations would follow several years later.

At this time we cannot accurately forecast the times when these different activities will occur.  Persons interested in employment opportunities or job training should monitor our website and social media site on Facebook for information on start-up of construction and operations:

Website: www.pumpkinhollowcopper.com

Facebook: https://www.facebook.com/miningRbusiness.

TYPES OF MINING CAREERS

  • Mining engineers
  • Metallurgical engineers
  • Electrical engineers
  • Civil engineers
  • Mechanical engineers
  • Structural engineers
  • Environmental engineers
  • Geologists
  • Hydrologists
  • Accountants
  • Supply chain professionals
  • Underground miners
  • Surface miners
  • Equipment operators
  • Supervisors
  • Electricians
  • Mechanics
  • Hoist operators
  • Safety professionals
  • Environmental technicians
  • Information systems and technology specialists

In the future, after Nevada Copper has obtained financing and would be able to begin construction, prospective job applicants will be asked to register with Nevada JobConnect. That information will be provided on this website at that time.

In the event that the Pumpkin Hollow Project starts operations, the company anticipates directly employing 750-800 people at the mine for a period of approximately 18 years.  In addition there will be approximately 100-500 people employed during various stages of construction. Based on the 2.5 job multiplier (Nevada Mining Employment Impacts 2014 (Page 123)) direct,  indirect and induced employment created by Pumpkin Hollow could be approximately 2,500.  Historically, mining jobs are among the highest-paying positions in Nevada. Nevada Mining Association reports that the average miner in Nevada earns $91,936 per year (Nevada Mining Industry Average Wages, page 114).

The Pumpkin Hollow project is still in the planning stages, so please check this website periodically to monitor project development and possible future employment.